Company or firm · first RERA registration 2017

Concorde Associates

Deedo IDDD-XHBA

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 62 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay62 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Cosmos HabitateP51700006637Thane (M Corp.)Certificate Signed31 Mar 201931 Mar 2019On date
Cosmos Habitate A WingP51700015427Thane (M Corp.)Certificate Signed30 Sep 202130 Jun 2024+62 mo*

Concorde Associates, in questions

Does Concorde Associates finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 62 mo late. Across Maharashtra, 73% kept their date.

How many projects has Concorde Associates registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Concorde Associates have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology