Concorde Associates
Deedo IDDD-XHBAOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 62 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Cosmos HabitateP51700006637 | Thane (M Corp.) | Certificate Signed | 31 Mar 2019 | 31 Mar 2019 | On date |
| Cosmos Habitate A WingP51700015427 | Thane (M Corp.) | Certificate Signed | 30 Sep 2021 | 30 Jun 2024 | +62 mo* |
Concorde Associates, in questions
Does Concorde Associates finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 62 mo late. Across Maharashtra, 73% kept their date.
How many projects has Concorde Associates registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Concorde Associates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.