Company or firm · first RERA registration 2017
City Corporation Limited
Of 9 registrations whose promised date has arrived, 9 were never extended past it (100%).
Projects813 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
4 registrations of 13 moved past the RERA date
Months late against the original RERA promise, per registration
Show all 13 registrations
13 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Amanora GatewayP52100000321 | Hadapsar | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Amanora GatewayP52100000380 | Hadapsar | Certificate Signed | 29 Apr 2022 | 29 Apr 2022 | On date |
| Amanora Adreno TowersP52100001822 | Hadapsar | Certificate Signed | 30 Mar 2022 | 30 Mar 2022 | On date |
| Amanora Sweet Water Villa PlotsP52100004890 | Hadapsar | Certificate Signed | 30 Sep 2018 | 30 Sep 2018 | On date |
| Amanora GoldP52100017612 | Hadapsar | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Amanora GoldP52100017962 | Hadapsar | Certificate Signed | 30 May 2024 | 30 May 2024 | On date |
| Amanora Ascent Towers 48 and 49P52100030032 | Hadapsar | Certificate Signed | 30 Sep 2025 | 30 Sep 2025 | On date |
| Amanora Elevate Tower 47P52100032079 | Hadapsar | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Amanora Ascent AvenueP52100047453 | Hadapsar | Certificate Signed | 12 Sep 2025 | 12 Sep 2025 | On date |
| Amanora ArbanoP52100052019 | Hadapsar | Certificate Signed | 31 May 2028 | 30 Sep 2028 | +4 mo |
| Amanora ArbanoP52100052614 | Hadapsar | Certificate Signed | 31 May 2028 | 30 Sep 2028 | +4 mo |
| Amanora GatewayP52100079477 | Hadapsar | Certificate Signed | 30 Jun 2029 | 30 Oct 2029 | +4 mo |
| Amanora GatewayPR1261012500749 | Hadapsar | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
Show all 13 registrationsShow fewer
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology