Choice Shelters

Deedo IDDD-CHAR

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 33 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay33 mowhen late · Maharashtra: 4 mo
First sales on record177registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Goodwill SquareP52100008756DhanoriCertificate Signed31 Mar 201810 Dec 2020+33 mo

Choice Shelters, in questions

Does Choice Shelters finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 33 mo late. Across Maharashtra, 73% kept their date.

How many projects has Choice Shelters registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Choice Shelters have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology