Company or firm · first RERA registration 2017

Bright Sky Heights Builders And Developers Private Limited

Deedo IDDD-XAFH

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 44 mo late.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay44 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases7no insolvency

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
complaintGalaxyComplaint CC006000000055911Not on record
complaintGalaxyComplaint CC006000000193160Not on record
complaintGalaxyComplaint CC006000000195959Not on record
complaintGalaxyComplaint CC12500065Not on record
appealGalaxyAppeal AT006000000144295/23Not on record
appealGalaxyAppeal AT006000000052994/21Not on record
appealGalaxyAppeal AT006000000021461/19Not on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
GalaxyP51700005683Thane (M Corp.)Certificate Signed31 May 201831 Oct 2018+5 mo
GalaxyP51700009788Thane (M Corp.)Lapsed31 Dec 2019—+83 mo*

Bright Sky Heights Builders And Developers Private Limited, in questions

Does Bright Sky Heights Builders And Developers Private Limited finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 44 mo late. Across Maharashtra, 73% kept their date.

How many projects has Bright Sky Heights Builders And Developers Private Limited registered with MahaRERA?

1 project under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Bright Sky Heights Builders And Developers Private Limited have MahaRERA regulatory cases?

7 regulatory cases name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology