Brickscity Developers Private Limited
Deedo IDDD-ZJRROf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 39 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Pride Of UttanP51700030690 | Mira Bhayandar (M Corp.) | Certificate Signed | 27 May 2022 | 31 Dec 2025 | +54 mo* |
| Bricks ManishaP51700032634 | Mirabhayandar (M Corp.) | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +23 mo* |
Brickscity Developers Private Limited, in questions
Does Brickscity Developers Private Limited finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 39 mo late. Across Maharashtra, 73% kept their date.
How many projects has Brickscity Developers Private Limited registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Brickscity Developers Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.