Bobhate Builders & Developers Pvt. Ltd
Deedo IDDD-S02NOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 23 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sudarshan ApartmentP51600010733 | Nashik (M Corp.) | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Sunandan ApartmentP51600032987 | Nashik | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +23 mo* |
Bobhate Builders & Developers Pvt. Ltd, in questions
Does Bobhate Builders & Developers Pvt. Ltd finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.
How many projects has Bobhate Builders & Developers Pvt. Ltd registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Bobhate Builders & Developers Pvt. Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.