Company or firm · first RERA registration 2019

Blue Pearl Realtors

Deedo IDDD-8GBK

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 37 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay37 mowhen late
First sales on record96registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
18 CasitaP52100023151BanerCertificate Signed2 Oct 20232 Oct 2023+37 mo*

Blue Pearl Realtors, in questions

Does Blue Pearl Realtors finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 37 mo late. Across Maharashtra, 73% kept their date.

How many projects has Blue Pearl Realtors registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Blue Pearl Realtors have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology