Bhavya Infrastructures India Private Limited
Deedo IDDD-P10VOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 82 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Listed as an NCLT insolvency project | Bhavya HeightsListed as NCLT project: Bhavya Heights | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Bhavya HeightsP51800003431 | Borivali | Certificate Signed | 31 Dec 2019 | 30 Sep 2022 | +82 mo* |
Bhavya Infrastructures India Private Limited, in questions
Does Bhavya Infrastructures India Private Limited finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 82 mo late. Across Maharashtra, 73% kept their date.
How many projects has Bhavya Infrastructures India Private Limited registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Bhavya Infrastructures India Private Limited have MahaRERA regulatory cases?
1 regulatory case name its registrations, including an insolvency (NCLT) case.