Bharatchandra Jeram Thakker

Deedo IDDD-ZW4K

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 44 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay44 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shivji KrupaP51900018231MatungaCertificate Signed30 Mar 202330 Sep 2025+44 mo*

Bharatchandra Jeram Thakker, in questions

Does Bharatchandra Jeram Thakker finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 44 mo late. Across Maharashtra, 73% kept their date.

How many projects has Bharatchandra Jeram Thakker registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Bharatchandra Jeram Thakker have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology