Company or firm · first RERA registration 2017

Bhagwati Developers

Deedo IDDD-V5H8

Of 5 registrations whose promised date has arrived, 4 kept it (80%). The rest ran a median 14 mo late.

Projects46 RERA registrations
Kept RERA date80%Maharashtra: 73%
Median delay14 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases2no insolvency

Delivery record

2 of 6 registrations with dates moved or missed their RERA date · months late against the original promise

6 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Bhagwati EleganzaP51700003864Navi Mumbai (M Corp.)Certificate Signed31 Dec 201831 Dec 2018On date
Bhagwati GreensP52000003952KhargharCertificate Signed31 Dec 202431 Dec 2024On date
Bhagwati ImperiaP52000004807UlaweCertificate Signed31 Dec 201831 Dec 2018On date
Bhagwati GreensP52000006596KhargharCertificate Signed31 Dec 202431 Dec 2024+23 mo*
Bhagwati GreensP52000006873KhargharCertificate Signed31 Dec 201931 Dec 2019On date
CelestriaP51700055856Navi Mumbai (M Corp.)Certificate Signed30 Jun 203030 Oct 2030+4 mo

Bhagwati Developers, in questions

Does Bhagwati Developers finish projects on time?

Of 5 MahaRERA registrations whose promised completion date has arrived, 4 kept it (80%). The rest ran a median 14 mo late. Across Maharashtra, 73% kept their date.

How many projects has Bhagwati Developers registered with MahaRERA?

4 projects under 6 MahaRERA registrations; 4 completed on MahaRERA.

Does Bhagwati Developers have MahaRERA regulatory cases?

2 regulatory cases name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology