Skip to content
Company or firm · first RERA registration 2024

Basil Promoters LLP

Deedo IDDD-ZKQP

None of 2 registrations has reached its promised completion date yet.

Projects12 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record188registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Basil VrundavanP52100056440Ambegaon BkCertificate Signed30 Apr 202830 Aug 2028+4 mo
Basil VrundavanPR1261012501486Ambegaon BkCertificate Signed31 Dec 202830 Apr 2029+4 mo

Basil Promoters LLP, in questions

Does Basil Promoters LLP finish projects on time?

None of its 2 MahaRERA registrations has reached its promised completion date yet.

How many projects has Basil Promoters LLP registered with MahaRERA?

1 project under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Basil Promoters LLP have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology