Company or firm · first RERA registration 2019

Baner Land Developers LLP

Deedo IDDD-1Z2H

None of 3 registrations has reached its promised completion date yet.

Projects13 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delayNone due yetwhen late · Maharashtra: 4 mo
First sales on record251registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 3 registrations with dates has moved or missed its RERA date

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Solitaire Business HubP52100022782BanerCertificate Signed31 Dec 202631 Dec 2026On date
Solitaire Business HubP52100024890BanerCertificate Signed31 Dec 202631 Dec 2026On date
Solitaire Business HubP52100025108BanerCertificate Signed31 Dec 202631 Dec 2026On date

Baner Land Developers LLP, in questions

Does Baner Land Developers LLP finish projects on time?

None of its 3 MahaRERA registrations has reached its promised completion date yet.

How many projects has Baner Land Developers LLP registered with MahaRERA?

1 project under 3 MahaRERA registrations; 0 completed on MahaRERA.

Does Baner Land Developers LLP have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology