Balaji Corporation Private Limited

Deedo IDDD-E3TA

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 83 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay83 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
VertuP51900005401Ward FnorthCertificate Signed31 Dec 201930 Dec 2021+83 mo*

Balaji Corporation Private Limited, in questions

Does Balaji Corporation Private Limited finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 83 mo late. Across Maharashtra, 73% kept their date.

How many projects has Balaji Corporation Private Limited registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Balaji Corporation Private Limited have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.