Bafna Builders And Land Developers

Deedo IDDD-JTR7

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay12 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases2no insolvency

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
complaintAnmol Nayantara GoldComplaint CC12503257Not on record
appealAnmol Nayantara GoldAppeal AT03/01572/2026Not on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Anmol Nayantara EmpireP51600001304NashikCertificate Signed31 Dec 201831 Dec 2019+12 mo
Anmol Nayantara GoldP51600002894NashikCompleted31 Dec 201831 Dec 2019+12 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology