Company or firm · first RERA registration 2017
Bafna Builders And Land Developers
Deedo IDDD-JTR7Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay12 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases2no insolvency
2 registrations of 2 ran past the RERA date
Months late against the original RERA promise, per registration
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| complaint | Anmol Nayantara GoldComplaint CC12503257 | Not on record |
| appeal | Anmol Nayantara GoldAppeal AT03/01572/2026 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Anmol Nayantara EmpireP51600001304 | Nashik | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Anmol Nayantara GoldP51600002894 | Nashik | Completed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology