Skip to content
Company or firm · first RERA registration 2025

B U Bhandari Buildcon Llp

Deedo IDDD-VH67

None of 1 registration has reached its promised completion date yet.

Projects11 RERA registration
Kept RERA dateNone due yetMaharashtra: 73%
Median delayNone due yetwhen late · Maharashtra: 4 mo
First sales on record19registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 1 registration with dates has moved or missed its RERA date

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
IndrashriP52100079940KothrudCertificate Signed30 Jun 202730 Jun 2027On date

B U Bhandari Buildcon Llp, in questions

Does B U Bhandari Buildcon Llp finish projects on time?

None of its 1 MahaRERA registration has reached its promised completion date yet.

How many projects has B U Bhandari Buildcon Llp registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does B U Bhandari Buildcon Llp have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology