Company or firm · first RERA registration 2017
B R Developers
Deedo IDDD-Z0PWOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 95 mo late.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay95 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Suo motu order | B R DevelopersSuo motu order: Secretary, MahaRERA Versus B. R. Developers (Suo Motu Case No. 90 of 2020) dated 18th February 2020 | 18 Feb 2020 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| B R DevelopersP52100010125 | Talegaon Dabhade (M Cl) | Certificate Signed | 30 Nov 2018 | 30 Nov 2018 | +95 mo* |
B R Developers, in questions
Does B R Developers finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 95 mo late. Across Maharashtra, 73% kept their date.
How many projects has B R Developers registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does B R Developers have MahaRERA regulatory cases?
1 regulatory case name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology