B J Hulawale Properties
Deedo IDDD-SBPKOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 36 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Quarterly progress report not filed | Laxmi PrideQuarterly progress report not filed: Laxmi Pride | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Laxmi PrideP52100027806 | Hinjavadi (Ct) | Not on record | 30 Jun 2022 | 30 Jun 2025 | +36 mo |
B J Hulawale Properties, in questions
Does B J Hulawale Properties finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 36 mo late. Across Maharashtra, 73% kept their date.
How many projects has B J Hulawale Properties registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does B J Hulawale Properties have MahaRERA regulatory cases?
1 regulatory case name its registrations.