Avishkar Developers
Deedo IDDD-X8CBOf 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 46 mo late.
Projects13 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay46 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Avishkar HeightsDeregistered: Avishkar Heights - A Wing - Phase Ii | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Avishkar HeightsP52800001154 | Jalgaon | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Avishkar HeightsP52800001535 | Jalgaon | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | +58 mo* |
| Avishkar HeightsP52800002837 | Jalgaon | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +34 mo* |
Avishkar Developers, in questions
Does Avishkar Developers finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 46 mo late. Across Maharashtra, 73% kept their date.
How many projects has Avishkar Developers registered with MahaRERA?
1 project under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Avishkar Developers have MahaRERA regulatory cases?
1 regulatory case name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology