Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 21 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay21 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sanskriti-NavyanganP52100000213Kasar AmboliCertificate Signed31 Mar 202030 Dec 2021+21 mo

Avior Merlin Buildcon Llp, in questions

Does Avior Merlin Buildcon Llp finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 21 mo late. Across Maharashtra, 73% kept their date.

How many projects has Avior Merlin Buildcon Llp registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Avior Merlin Buildcon Llp have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.