Assets Reality

Deedo IDDD-0EQ5

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 96 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay96 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases30no insolvency

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
complaintThe Chalets AvenueComplaint CC006000000044180Not on record
complaintThe Chalets AvenueComplaint CC006000000023906Not on record
complaintThe Chalets AvenueComplaint CC006000000057076Not on record
complaintThe Chalets AvenueComplaint CC006000000078285Not on record
complaintThe Chalets AvenueComplaint CC006000000078288Not on record
complaintThe Chalets AvenueComplaint CC006000000078290Not on record
complaintThe Chalets AvenueComplaint CC006000000078292Not on record
complaintThe Chalets AvenueComplaint CC006000000078293Not on record
complaintThe Chalets AvenueComplaint CC006000000078297Not on record
complaintThe Chalets AvenueComplaint CC006000000078299Not on record
complaintThe Chalets AvenueComplaint CC006000000078302Not on record
complaintThe Chalets AvenueComplaint CC006000000078303Not on record
complaintThe Chalets AvenueComplaint CC006000000078446Not on record
complaintThe Chalets AvenueComplaint CC006000000078479Not on record
complaintThe Chalets AvenueComplaint CC006000000078500Not on record
complaintThe Chalets AvenueComplaint CC006000000078535Not on record
complaintThe Chalets AvenueComplaint CC006000000078539Not on record
complaintThe Chalets AvenueComplaint CC006000000078542Not on record
complaintThe Chalets AvenueComplaint CC006000000078543Not on record
complaintThe Chalets AvenueComplaint CC006000000078609Not on record
complaintThe Chalets AvenueComplaint CC006000000196221Not on record
complaintThe Chalets AvenueComplaint CC006000000344216Not on record
complaintThe Chalets AvenueComplaint CC006000000397492Not on record
complaintThe Chalets AvenueComplaint CC12503106Not on record
complaintThe Chalets AvenueComplaint CC12503142Not on record
complaintThe Chalets AvenueComplaint CC12503144Not on record
complaintThe Chalets AvenueComplaint CC12602485Not on record
appealThe Chalets AvenueAppeal AT06/01497/2026Not on record
appealThe Chalets AvenueAppeal AT06/01323/2025Not on record
appealThe Chalets AvenueAppeal AT006000000010503/18Not on record
Show all 30 casesShow fewer

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
The Chalets AvenueP51700008568Badlapur (M Cl)Active30 Nov 2018—+96 mo*

Assets Reality, in questions

Does Assets Reality finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 96 mo late. Across Maharashtra, 73% kept their date.

How many projects has Assets Reality registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Assets Reality have MahaRERA regulatory cases?

30 regulatory cases name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology