Ashwini Builder's & Developers Pvt. Ltd
Deedo IDDD-1T5QOf 4 registrations whose promised date has arrived, 4 kept it (100%).
Delivery record
None of 5 registrations with dates has moved or missed its RERA date
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sonaashwini ResidencyP52700011287 | Vanvaswadi | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| KartikiashwiniP52700014192 | Vanvaswadi | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| LataashwiniP52700025746 | Vanvaswadi | Certificate Signed | 30 Sep 2024 | 30 Sep 2024 | On date |
| Arunaashwini ResidencyP52700029180 | Satara | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | On date |
| Spruhaashwini ResidencyP52700051489 | Vanvaswadi | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
Ashwini Builder's & Developers Pvt. Ltd, in questions
Does Ashwini Builder's & Developers Pvt. Ltd finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 4 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Ashwini Builder's & Developers Pvt. Ltd registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 5 completed on MahaRERA.
Does Ashwini Builder's & Developers Pvt. Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.