Deedo IDDD-N13DOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 50 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Swastik HeightsP51700028436 | Kalyan | Certificate Signed | 30 Sep 2022 | 30 Sep 2023 | +50 mo* |
Ashok Suryanarayan Singh, in questions
Does Ashok Suryanarayan Singh finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 50 mo late. Across Maharashtra, 73% kept their date.
How many projects has Ashok Suryanarayan Singh registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Ashok Suryanarayan Singh have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.