Ashok Baheti
Deedo IDDD-9HS6Of 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 49 mo late.
Delivery record
4 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| complaint | Hrim Ssky City Phase IComplaint CC003000000050144 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Hrim Ssky City Phase IP51500003143 | Aurangabad (M Corp.) | Lapsed | 30 Oct 2022 | — | +49 mo* |
| Hrim Ssky City Phase IIP51500003253 | Aurangabad (M Corp.) | Completed | 30 Oct 2022 | — | On date |
| Hrim Sky City Phase IIIP51500006796 | Aurangabad (M Corp.) | Certificate Signed | 30 Oct 2022 | 30 Oct 2022 | +49 mo* |
| Hrim Ssky City Phase IVP51500016766 | Satara (Ct) | Certificate Signed | 28 Apr 2023 | 31 Dec 2027 | +56 mo |
| Auric HomesP51500049985 | Gangapur Jahagir | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
Ashok Baheti, in questions
Does Ashok Baheti finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 1 kept it (25%). The rest ran a median 49 mo late. Across Maharashtra, 73% kept their date.
How many projects has Ashok Baheti registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 1 completed on MahaRERA.
Does Ashok Baheti have MahaRERA regulatory cases?
1 regulatory case name its registrations.