Aqura Builder & Developer Private Limited
Deedo IDDD-2ZMAOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.
Delivery record
4 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Aqura ParadiseP52100000498 | Pune (M Corp.) | Certificate Signed | 31 Jan 2020 | 30 Jun 2022 | +82 mo* |
| Aqura PrideP52100031863 | Wadgaon Bk | Certificate Signed | 28 Jan 2027 | 28 May 2027 | +4 mo |
| Aqura PrimeP52100078984 | Vadgaon Sheri | Certificate Signed | 30 Jul 2028 | 30 Nov 2028 | +4 mo |
| Aqura PridePM1260002501897 | Wadgaon Bk | Certificate Signed | 30 May 2028 | 30 Sep 2028 | +4 mo |
| Aqura IndraprasthaPM1260002601531 | Kothrud | Certificate Signed | 1 Apr 2030 | 1 Apr 2030 | On date |
| Aqura PridePM1260002601937 | Wadgaon Bk | Certificate Signed | 31 Dec 2029 | 31 Dec 2029 | On date |
Aqura Builder & Developer Private Limited, in questions
Does Aqura Builder & Developer Private Limited finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Aqura Builder & Developer Private Limited registered with MahaRERA?
5 projects under 6 MahaRERA registrations; 0 completed on MahaRERA.
Does Aqura Builder & Developer Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.