Aq Infrastructure Private Limited
Deedo IDDD-RNNQOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 15 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Aq HeightsP51500011237 | Aurangabad | Certificate Signed | 28 Feb 2021 | 28 Feb 2021 | On date |
| Aq TownP51500012659 | Aurangabad (M Corp.) | Active | 28 Aug 2025 | — | +15 mo* |
Aq Infrastructure Private Limited, in questions
Does Aq Infrastructure Private Limited finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 15 mo late. Across Maharashtra, 73% kept their date.
How many projects has Aq Infrastructure Private Limited registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Aq Infrastructure Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
