Apoorva Homes

Deedo IDDD-QMZN

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 24 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay24 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sahakar Nagar Grace Co-Op. Hsg. Soc. LtdP51800005727KurlaCertificate Signed31 Dec 201930 Dec 2021+24 mo

Apoorva Homes, in questions

Does Apoorva Homes finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 24 mo late. Across Maharashtra, 73% kept their date.

How many projects has Apoorva Homes registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Apoorva Homes have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology