Company or firm · first RERA registration 2018
Anukaran Consultancy Pvt Ltd
Deedo IDDD-RS6GOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 11 mo late.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay11 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases2no insolvency
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| complaint | PavillionComplaint CC004000000010093 | Not on record |
| complaint | PavillionComplaint CC004000000070587 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| PavillionP50500015447 | Nagpur (M Corp.) | Active | 30 Dec 2025 | — | +11 mo* |
Anukaran Consultancy Pvt Ltd, in questions
Does Anukaran Consultancy Pvt Ltd finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.
How many projects has Anukaran Consultancy Pvt Ltd registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Anukaran Consultancy Pvt Ltd have MahaRERA regulatory cases?
2 regulatory cases name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology