Anukaran Consultancy Pvt Ltd

Deedo IDDD-RS6G

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 11 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay11 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases2no insolvency

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
complaintPavillionComplaint CC004000000010093Not on record
complaintPavillionComplaint CC004000000070587Not on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
PavillionP50500015447Nagpur (M Corp.)Active30 Dec 2025—+11 mo*

Anukaran Consultancy Pvt Ltd, in questions

Does Anukaran Consultancy Pvt Ltd finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.

How many projects has Anukaran Consultancy Pvt Ltd registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Anukaran Consultancy Pvt Ltd have MahaRERA regulatory cases?

2 regulatory cases name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology