Anthurium Developers Limited

Deedo IDDD-W9MA

None of 2 registrations has reached its promised completion date yet.

Projects12 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Mahindra RainforestPM1181012502957KanjurmargCertificate Signed31 Dec 203130 Apr 2032+4 mo
Mahindra RainforestPR1181012502956KanjurmargCertificate Signed31 Dec 203130 Apr 2032+4 mo

Anthurium Developers Limited, in questions

Does Anthurium Developers Limited finish projects on time?

None of its 2 MahaRERA registrations has reached its promised completion date yet.

How many projects has Anthurium Developers Limited registered with MahaRERA?

1 project under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Anthurium Developers Limited have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology