Company or firm · first RERA registration 2022
Anshul Bhosale Realty Llp
Deedo IDDD-B8NDNone of 4 registrations has reached its promised completion date yet.
Projects44 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency
Delivery record
4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| complaint | Kosmas A WingComplaint CC005000000340780 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Anshul Kanvas B BuildingP52100045669 | Wagholi | Certificate Signed | 30 Apr 2028 | 30 Aug 2028 | +4 mo |
| Kosmas A WingP52100046506 | Moshi | Active | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| KOSMAS B1 WingP52100055984 | Moshi | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Anshul Medora C BuildingP52100079331 | Wagholi | Certificate Signed | 30 Apr 2030 | 30 Aug 2030 | +4 mo |
Anshul Bhosale Realty Llp, in questions
Does Anshul Bhosale Realty Llp finish projects on time?
None of its 4 MahaRERA registrations has reached its promised completion date yet.
How many projects has Anshul Bhosale Realty Llp registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.
Does Anshul Bhosale Realty Llp have MahaRERA regulatory cases?
1 regulatory case name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology