Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 14 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay14 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Anmol NirmitiP52000029326KaranjadeCertificate Signed31 Dec 202325 Feb 2025+14 mo

Anmol Nirmiti Pvt Ltd, in questions

Does Anmol Nirmiti Pvt Ltd finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 14 mo late. Across Maharashtra, 73% kept their date.

How many projects has Anmol Nirmiti Pvt Ltd registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Anmol Nirmiti Pvt Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology