Company or firm · first RERA registration 2018
Anjani Kumar Co Pvt Ltd
Of 1 registration whose promised date has arrived, 1 were never extended past it (100%).
Projects44 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen extended · Maharashtra: 4 mo
Completed0as reported on MahaRERA
Regulatory cases0none on record
3 registrations of 4 moved past the RERA date
Months late against the original RERA promise, per registration
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shiv GangaP51800017043 | Borivali | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
| The PentagonP51700047942 | Goteghar | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Anjani OneP51700050620 | Mirabhayandar (M Corp.) | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| Anjani BlissPM1330002600185 | Navghar | Certificate Signed | 31 Mar 2030 | 31 Jul 2030 | +4 mo |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology