Company or firm · first RERA registration 2017

Anchor Daewoo Industries Ltd

Deedo IDDD-N1YY

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 82 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay82 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
South RidgeP51900011067Ward AbcdCertificate Signed31 Jan 202030 Jan 2022+82 mo*

Anchor Daewoo Industries Ltd, in questions

Does Anchor Daewoo Industries Ltd finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 82 mo late. Across Maharashtra, 73% kept their date.

How many projects has Anchor Daewoo Industries Ltd registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Anchor Daewoo Industries Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology