Amol Ajit Ravetkar
Deedo IDDD-D6QSOf 6 registrations whose promised date has arrived, 3 kept it (50%). The rest ran a median 4 mo late.
Delivery record
11 of 16 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 16 registrations
16 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| PiyushaP52100002284 | Pune (M Corp.) | Certificate Signed | 31 Mar 2019 | 31 Mar 2019 | On date |
| SukhniwasP52100009654 | Pune (M Corp.) | Certificate Signed | 27 Feb 2022 | 30 Jun 2024 | +28 mo |
| 70 West AvenueP52100017946 | Erandwana | Certificate Signed | 30 Dec 2022 | 30 Sep 2024 | +21 mo |
| Shri-OmP52100019369 | Pune (M Corp.) | Certificate Signed | 30 Jun 2022 | 30 Jun 2022 | On date |
| AnushreeP52100024833 | Kothrud | Certificate Signed | 15 Feb 2025 | 15 Feb 2025 | On date |
| JanhaviP52100028769 | Kothrud-North | Certificate Signed | 18 Nov 2026 | 18 Nov 2026 | On date |
| SwargandhaP52100046968 | Haveli | Certificate Signed | 30 Apr 2029 | 30 Apr 2029 | On date |
| HrishikeshP52100050088 | Shivajinagar Bhamburda | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| AditiP52100050632 | Kothrud | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| Shri KeshavlaxmiP52100053892 | Kothrud | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 mo |
| SumanP52100054831 | Erandwana | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| ArishaP52100055981 | Erandwana | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
| NiveditaPR1260002500589 | Kothrud | Certificate Signed | 31 Mar 2029 | 31 Jul 2029 | +4 mo |
| Nirmitee ViharPR1260002500783 | Kothrud | Certificate Signed | 31 Aug 2028 | 31 Dec 2028 | +4 mo |
| ShivsudhaPR1260002501282 | Kothrud | Certificate Signed | 30 Jun 2029 | 30 Oct 2029 | +4 mo |
| SumukhPR1260002502924 | Shivajinagar Bhamburda | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
Show all 16 registrationsShow fewer
Amol Ajit Ravetkar, in questions
Does Amol Ajit Ravetkar finish projects on time?
Of 6 MahaRERA registrations whose promised completion date has arrived, 3 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Amol Ajit Ravetkar registered with MahaRERA?
16 projects under 16 MahaRERA registrations; 5 completed on MahaRERA.
Does Amol Ajit Ravetkar have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.