Ameya Enterprises
Deedo IDDD-KDS7Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 14 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Nav Anuradha Darshan Chs LtdP51700021310 | Kalyan-Dombivali (M Corp.) | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | +23 mo* |
| Komal Palace CHS LTDP51700078402 | Dombivli | Certificate Signed | 30 Sep 2029 | 30 Jan 2030 | +4 mo |
Ameya Enterprises, in questions
Does Ameya Enterprises finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 14 mo late. Across Maharashtra, 73% kept their date.
How many projects has Ameya Enterprises registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Ameya Enterprises have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.