Deedo IDDD-3A4BNone of 1 registration has reached its promised completion date yet.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Amey Hi Life Wing C & DPR1151012500763 | Kolhapur (M Corp.) | Certificate Signed | 31 Dec 2032 | 30 Apr 2033 | +4 mo |
Amey Estates, in questions
Does Amey Estates finish projects on time?
None of its 1 MahaRERA registration has reached its promised completion date yet.
How many projects has Amey Estates registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Amey Estates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.