Company or firm · first RERA registration 2023
Ambit Builders & Developers
Deedo IDDD-W1SKOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 11 mo late.
Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay11 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases2no insolvency
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| complaint | Ambit VistaComplaint CC006000000480134 | Not on record |
| appeal | Ambit VistaAppeal AT06/01272/2025 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ambit VistaP51800052265 | Vileparle | Active | 31 Dec 2025 | — | +11 mo* |
Ambit Builders & Developers, in questions
Does Ambit Builders & Developers finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.
How many projects has Ambit Builders & Developers registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Ambit Builders & Developers have MahaRERA regulatory cases?
2 regulatory cases name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology