Skip to content
Company or firm · first RERA registration 2017

Ambience Developments

Deedo IDDD-WQ07

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 54 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay54 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Ambience Greendale Wing DP52100002295Pune (M Corp.)Certificate Signed31 Mar 201930 Sep 2023+54 mo

Ambience Developments, in questions

Does Ambience Developments finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 54 mo late. Across Maharashtra, 73% kept their date.

How many projects has Ambience Developments registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Ambience Developments have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology