Ajk Realty
Deedo IDDD-3KR3Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 11 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| AranyaP52100016387 | Bavdhan Kh. | Certificate Signed | 30 May 2022 | 30 Apr 2023 | +11 mo |
Ajk Realty, in questions
Does Ajk Realty finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.
How many projects has Ajk Realty registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Ajk Realty have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.