Individual promoter · first RERA registration 2018

Afzal Umer Furniturewala

Deedo IDDD-CY4B

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 25 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay25 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Deccan SquareP52000018283PenCertificate Signed30 Oct 202430 Oct 2024+25 mo*

Afzal Umer Furniturewala, in questions

Does Afzal Umer Furniturewala finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 25 mo late. Across Maharashtra, 73% kept their date.

How many projects has Afzal Umer Furniturewala registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Afzal Umer Furniturewala have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology