Aditya Shagun Developers
Deedo IDDD-8Z9VOf 7 registrations whose promised date has arrived, 7 kept it (100%).
Delivery record
1 of 8 registrations with dates moved or missed their RERA date · months late against the original promise
8 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Nisarg PalmsP52100002025 | Bavadhan Bk | Certificate Signed | 30 Jun 2018 | 30 Jun 2018 | On date |
| Comfort Zone NestP52100005265 | Baner | Certificate Signed | 11 Jul 2018 | 11 Jul 2018 | On date |
| Nisarg TulipsP52100014405 | Haveli | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Comfort ZoneP52100014406 | Balewadi | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Comfort Zone PlusP52100014407 | Balewadi | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Nisarg PalmsP52100015113 | Haveli | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Comfort Zone Nest Project TwoP52100016685 | Balewadi | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Comfort Zone BlissPR1260002501819 | Balewadi | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
Aditya Shagun Developers, in questions
Does Aditya Shagun Developers finish projects on time?
Of 7 MahaRERA registrations whose promised completion date has arrived, 7 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Aditya Shagun Developers registered with MahaRERA?
8 projects under 8 MahaRERA registrations; 7 completed on MahaRERA.
Does Aditya Shagun Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.