Company or firm · first RERA registration 2017

Aditya Enterprise Project Ekta

Deedo IDDD-MCP8

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 76 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay76 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Ekta Apartment Upto 17th FloorP51800009361BorivaliCertificate Signed31 Mar 201928 Feb 2026+92 mo*
Ekta Appartment From 18th Floor To 22nd FloorP51800011046BorivaliCertificate Signed30 Dec 202131 Dec 2026+60 mo

Aditya Enterprise Project Ekta, in questions

Does Aditya Enterprise Project Ekta finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 76 mo late. Across Maharashtra, 73% kept their date.

How many projects has Aditya Enterprise Project Ekta registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Aditya Enterprise Project Ekta have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology