Company or firm · first RERA registration 2017

Aditya Associates

Deedo IDDD-YJEA

Of 8 registrations whose promised date has arrived, 5 kept it (63%). The rest ran a median 11 mo late.

Projects1010 RERA registrations
Kept RERA date63%Maharashtra: 73%
Median delay11 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

5 of 10 registrations with dates moved or missed their RERA date · months late against the original promise

10 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Kamal ResidencyP52100002337Talegaon Dabhade (R)Certificate Signed31 Mar 201931 Mar 2019On date
Aditya ViharP52100002988Talegaon Dabhade (R)Certificate Signed30 Sep 201830 Sep 2018On date
Little CherryP52100015563Talegaon Dabhade (R)Certificate Signed31 Dec 201931 Dec 2019On date
LotusP52100018098Talegaon Dabhade (R)Certificate Signed30 Mar 202130 Mar 2021On date
Sai VatikaP52100021148MawalCertificate Signed30 Oct 202230 Oct 2022On date
Shanti KunjP52100029636Talegaon Dabhade (R)Certificate Signed30 Jun 202430 Jun 2024+29 mo*
Sai KrupaP52100029947Talegaon Dabhade (R)Certificate Signed30 Jun 202430 Jun 2024+29 mo*
Sai PlazaP52100045714Talegaon Dabhade (R)Certificate Signed31 Dec 202531 Dec 2025+11 mo*
Sai ParadiseP52100076594Talegaon Dabhade (R)Certificate Signed24 Nov 202724 Mar 2028+4 mo
SonaiP52100079913Talegaon Dabhade (R)Certificate Signed30 Jun 202730 Oct 2027+4 mo

Aditya Associates, in questions

Does Aditya Associates finish projects on time?

Of 8 MahaRERA registrations whose promised completion date has arrived, 5 kept it (63%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.

How many projects has Aditya Associates registered with MahaRERA?

10 projects under 10 MahaRERA registrations; 5 completed on MahaRERA.

Does Aditya Associates have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology