Aditya Associates
Deedo IDDD-YJEAOf 8 registrations whose promised date has arrived, 5 kept it (63%). The rest ran a median 11 mo late.
Delivery record
5 of 10 registrations with dates moved or missed their RERA date · months late against the original promise
10 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Kamal ResidencyP52100002337 | Talegaon Dabhade (R) | Certificate Signed | 31 Mar 2019 | 31 Mar 2019 | On date |
| Aditya ViharP52100002988 | Talegaon Dabhade (R) | Certificate Signed | 30 Sep 2018 | 30 Sep 2018 | On date |
| Little CherryP52100015563 | Talegaon Dabhade (R) | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| LotusP52100018098 | Talegaon Dabhade (R) | Certificate Signed | 30 Mar 2021 | 30 Mar 2021 | On date |
| Sai VatikaP52100021148 | Mawal | Certificate Signed | 30 Oct 2022 | 30 Oct 2022 | On date |
| Shanti KunjP52100029636 | Talegaon Dabhade (R) | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | +29 mo* |
| Sai KrupaP52100029947 | Talegaon Dabhade (R) | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | +29 mo* |
| Sai PlazaP52100045714 | Talegaon Dabhade (R) | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
| Sai ParadiseP52100076594 | Talegaon Dabhade (R) | Certificate Signed | 24 Nov 2027 | 24 Mar 2028 | +4 mo |
| SonaiP52100079913 | Talegaon Dabhade (R) | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
Aditya Associates, in questions
Does Aditya Associates finish projects on time?
Of 8 MahaRERA registrations whose promised completion date has arrived, 5 kept it (63%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.
How many projects has Aditya Associates registered with MahaRERA?
10 projects under 10 MahaRERA registrations; 5 completed on MahaRERA.
Does Aditya Associates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.