Adhya Properties
Deedo IDDD-XQB2Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 5 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Regulatory order | Adhya Radha KrishnaRegulatory order: PROJECT NAME: ADHYA RADHA KRISHNA (Regulatory Case No.96 of 2023) dated 22 November 2023. | 25 Nov 2023 |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Adhya RohanP52100001122 | Manchar (Ct) | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Adhya Radha KrishnaP52100001891 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 31 Mar 2027 | 31 Mar 2027 | On date |
| Adhya AbhiP52000024248 | Karanjade | Certificate Signed | 30 Dec 2022 | 30 Jun 2023 | +6 mo |
| Adhya Radhakrishna C WingP52100031702 | Chikhali | Certificate Signed | 31 Oct 2026 | 28 Feb 2027 | +4 mo |
Adhya Properties, in questions
Does Adhya Properties finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 5 mo late. Across Maharashtra, 73% kept their date.
How many projects has Adhya Properties registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.
Does Adhya Properties have MahaRERA regulatory cases?
1 regulatory case name its registrations.