Ace Constructions

Deedo IDDD-F453

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 31 mo late.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay31 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases0none on record

2 registrations of 2 ran past the RERA date

Months late against the original RERA promise, per registration

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
AnuthamP52100000820HadapsarCertificate Signed30 Dec 202130 Dec 2021+58 mo*
AnuthamP52100020764HadapsarCertificate Signed30 Sep 202630 Jan 2027+4 mo
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology