Anutham

Certificate Signed

Hadapsar, Pune 411028 |Promoter: Ace Constructions

23 Jul 2017Registered with MahaRERAFirst of 2 registrations
30 Sep 2026Promised completionLatest across registrations
30 Jan 2027Revised completion1 of 2 registrations pushed back, by up to 4 months
4Buildings2 phases
314Units registered303 booked (96%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
RERA registrations
2
Phases
2
Buildings
4
Unit types
1.5 BHK, 1BHK, 2.5 BHK, 2BHK, 3.5 BHK (DUPLEX), 3BHK, 3 BHK (DUPLEX), Office space, Shop, 1RK, 2 BHK, 3 BHK, 1 BHK314 units in all
Address
257A, Pune Solapur Road, HadpsarPIN 411028
Designated bank account
87
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.50154, 73.92672
Anutham is at latitude 18.50154, longitude 73.92672.

Also registered as

Anutham Phase 1Anutham Phase II

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Dec 2021

P52100000820

The latest completion date on record passed 4 years and 10 months ago.

Registered
23 Jul 2017
Promised
30 Dec 2021

Completion pushed back 4 months

P52100020764
Registered
8 May 2019
Promised
30 Sep 2026
Revised
30 Jan 2027

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210000082023 Jul 201730 Dec 202130 Dec 2021Ace ConstructionsProject page
P521000207648 May 201930 Sep 202630 Jan 2027Ace ConstructionsProject page

4 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A21188
B1240
B22364
C2362

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

303 of 314 units booked (96%), as the promoter reported to MahaRERA

1.5 BHK · 12 units1BHK · 3 units2.5 BHK · 7 units2BHK · 90 units3.5 BHK (DUPLEX) · 2 units3BHK · 50 units3 BHK (DUPLEX) · 8 unitsOffice space · 5 unitsShop · 23 units1RK · 0 units2 BHK · 74 units3 BHK · 30 units1 BHK · 10 units
RERABuildingTypeCarpet areaUnitsBooked
P52100020764A1.5 BHK58.85 sq m · 633 sq ft11
P52100020764A1.5 BHK59.21 sq m · 637 sq ft22
P52100020764A1.5 BHK59.48 sq m · 640 sq ft22
P52100020764A1.5 BHK61.3 sq m · 660 sq ft11
P52100020764A1.5 BHK65.77 sq m · 708 sq ft11
P52100020764A1.5 BHK66.09 sq m · 711 sq ft22
P52100020764A1.5 BHK66.4 sq m · 715 sq ft11
P52100020764A1.5 BHK67.92 sq m · 731 sq ft22
Show all 77 unit rowsShow fewer unit rows
RERABuildingTypeCarpet areaUnitsBooked
P52100020764A1BHK39.75 sq m · 428 sq ft11
P52100020764A1BHK46.23 sq m · 498 sq ft11
P52100020764A1BHK55 sq m · 592 sq ft11
P52100020764A2.5 BHK72.98 sq m · 786 sq ft11
P52100020764A2.5 BHK74.63 sq m · 803 sq ft22
P52100020764A2.5 BHK79.44 sq m · 855 sq ft11
P52100020764A2.5 BHK80.79 sq m · 870 sq ft11
P52100020764A2.5 BHK81.38 sq m · 876 sq ft22
P52100020764A2BHK65.14 sq m · 701 sq ft1010
P52100020764A2BHK65.32 sq m · 703 sq ft55
P52100020764A2BHK65.57 sq m · 706 sq ft66
P52100020764A2BHK66.8 sq m · 719 sq ft99
P52100020764A2BHK74.18 sq m · 798 sq ft77
P52100020764A2BHK74.23 sq m · 799 sq ft1413
P52100020764A2BHK74.29 sq m · 800 sq ft22
P52100020764A2BHK74.4 sq m · 801 sq ft22
P52100020764A2BHK74.43 sq m · 801 sq ft66
P52100020764A2BHK74.47 sq m · 802 sq ft11
P52100020764A2BHK74.72 sq m · 804 sq ft11
P52100020764A2BHK75.88 sq m · 817 sq ft22
P52100020764A2BHK75.95 sq m · 818 sq ft1313
P52100020764A3.5 BHK (DUPLEX)153.54 sq m · 1,653 sq ft21
P52100020764A3BHK79.5 sq m · 856 sq ft55
P52100020764A3BHK80.4 sq m · 865 sq ft44
P52100020764A3BHK80.94 sq m · 871 sq ft1010
P52100020764A3BHK88.35 sq m · 951 sq ft77
P52100020764A3BHK88.65 sq m · 954 sq ft11
P52100020764A3BHK88.87 sq m · 957 sq ft65
P52100020764A3BHK89.53 sq m · 964 sq ft1414
P52100020764A3BHK89.55 sq m · 964 sq ft11
P52100020764A3BHK89.81 sq m · 967 sq ft22
P52100020764A3 BHK (DUPLEX)115.31 sq m · 1,241 sq ft21
P52100020764A3 BHK (DUPLEX)115.41 sq m · 1,242 sq ft20
P52100020764A3 BHK (DUPLEX)116.57 sq m · 1,255 sq ft21
P52100020764A3 BHK (DUPLEX)121.64 sq m · 1,309 sq ft22
P52100020764AOffice space22.95 sq m · 247 sq ft11
P52100020764AOffice space35.55 sq m · 383 sq ft11
P52100020764AOffice space84.76 sq m · 912 sq ft11
P52100020764AOffice space87.53 sq m · 942 sq ft11
P52100020764AOffice space142.92 sq m · 1,538 sq ft11
P52100020764AShop17.08 sq m · 184 sq ft22
P52100020764AShop19 sq m · 205 sq ft11
P52100020764AShop19.13 sq m · 206 sq ft33
P52100020764AShop19.29 sq m · 208 sq ft22
P52100020764AShop20.08 sq m · 216 sq ft22
P52100020764AShop21.19 sq m · 228 sq ft21
P52100020764AShop25.14 sq m · 271 sq ft11
P52100020764AShop25.35 sq m · 273 sq ft11
P52100020764AShop28.06 sq m · 302 sq ft11
P52100020764AShop32.98 sq m · 355 sq ft10
P52100020764AShop38.12 sq m · 410 sq ft11
P52100020764AShop42.21 sq m · 454 sq ft11
P52100020764AShop50.09 sq m · 539 sq ft42
P52100020764AShop50.5 sq m · 544 sq ft11
P52100020764B11RK—00
P52100000820B22 BHK51.05 sq m · 549 sq ft3232
P52100000820B22 BHK51.79 sq m · 557 sq ft22
P52100000820B23 BHK68.49 sq m · 737 sq ft3030
P52100000820C1 BHK31.47 sq m · 339 sq ft1010
P52100000820C2 BHK32.08 sq m · 345 sq ft88
P52100000820C2 BHK32.18 sq m · 346 sq ft1414
P52100000820C2 BHK32.19 sq m · 346 sq ft22
P52100000820C2 BHK36.28 sq m · 391 sq ft88
P52100000820C2 BHK46.25 sq m · 498 sq ft44
P52100000820C2 BHK46.4 sq m · 499 sq ft44
P52100000820C2BHK40.34 sq m · 434 sq ft11
P52100000820C2BHK40.63 sq m · 437 sq ft88
P52100000820C2BHK40.64 sq m · 437 sq ft11
P52100000820C2BHK43 sq m · 463 sq ft22

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 250 filings listed on MahaRERA's project page

Registration certificate (2)

  • Registration certificateP52100000820 · 9 Sep 2021ViewSource
  • Registration certificateP52100020764 · 11 Sep 2026ViewSource

Finance

  • PAN CardP52100000820 · PAN CARD ACE.pdf · uploaded 19 Jul 2017Source
  • PAN CardP52100020764 · PAN CARD ACE.pdf · uploaded 4 May 2019Source
  • Other – FinanceP52100000820 · Anutham C wing Form 4.pdf · uploaded 16 Feb 2023Source
  • Other – FinanceP52100000820 · Anutham B2 wing Form 4.pdf · uploaded 16 Feb 2023Source

Legal

  • Legal Title reportP52100000820 · Anutham Search Report.pdf · uploaded 19 Jul 2017Source
  • Declaration Form BP52100000820 · FORM B ANUTHAM.pdf · uploaded 19 Jul 2017Source
Show all 252 documentsShow fewer documents

Legal

  • Legal Title reportP52100020764 · Anutham Search Report.pdf · uploaded 4 May 2019Source
  • Declaration Form BP52100020764 · FORM B ANUTHAM.pdf · uploaded 4 May 2019Source
  • Declaration Form BP52100020764 · Form B.pdf · uploaded 19 Jul 2024Source

Migrated

  • 1 PAN CardP52100000820 · PAN CARD ACE.pdf · uploaded 19 Jul 2017Source
  • 1 Copy of the legal title reportP52100000820 · Anutham Search Report.pdf · uploaded 19 Jul 2017Source
  • 1 Details of encumbrancesP52100000820 · encumbrances Certificate - Hadapsar.pdf · uploaded 19 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)P52100000820 · Layout.pdf · uploaded 19 Jul 2017Source
  • 1 Building Plan Approval (IOD)P52100000820 · ANUTHAM Amalgamation.pdf · uploaded 19 Jul 2017Source
  • 2 Building Plan Approval (IOD)P52100000820 · ANUTHAM B1 B2.pdf · uploaded 19 Jul 2017Source
  • 3 Building Plan Approval (IOD)P52100000820 · ANUTHAM C.pdf · uploaded 19 Jul 2017Source
  • 4 Building Plan Approval (IOD)P52100000820 · ANUTHAM C-.pdf · uploaded 19 Jul 2017Source
  • 5 Building Plan Approval (IOD)P52100000820 · ANUTHAM Elevation ABC.pdf · uploaded 19 Jul 2017Source
  • 6 Building Plan Approval (IOD)P52100000820 · ANUTHAM LIG.pdf · uploaded 19 Jul 2017Source
  • 7 Building Plan Approval (IOD)P52100000820 · ANUTHAM Parking Layout.pdf · uploaded 19 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100000820 · CC.pdf · uploaded 19 Jul 2017Source
  • 1 Declaration in FORM BP52100000820 · FORM B ANUTHAM.pdf · uploaded 19 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000820 · Jideep Deshpande.pdf · uploaded 19 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000820 · Engg - form 2 - s Patil.pdf · uploaded 19 Jul 2017Source
  • 1 Certificates of CA (Form 3)P52100000820 · C A - Certificate - anutham.pdf · uploaded 19 Jul 2017Source
  • 1 Proforma of Allotment letterP52100000820 · Unit Agreement Hadapsar.pdf · uploaded 19 Jul 2017Source
  • 2 Proforma of Allotment letterP52100000820 · Unit Agreement Hadapsar - updated.pdf · uploaded 10 Nov 2017Source
  • 8 Building Plan Approval (IOD)P52100000820 · 1-8.pdf · uploaded 11 Jan 2018Source
  • 9 Building Plan Approval (IOD)P52100000820 · 2-8.pdf · uploaded 11 Jan 2018Source
  • 10 Building Plan Approval (IOD)P52100000820 · 3-8.pdf · uploaded 11 Jan 2018Source
  • 11 Building Plan Approval (IOD)P52100000820 · 4-8.pdf · uploaded 11 Jan 2018Source
  • 12 Building Plan Approval (IOD)P52100000820 · 5-8.pdf · uploaded 11 Jan 2018Source
  • 13 Building Plan Approval (IOD)P52100000820 · 6-8.pdf · uploaded 11 Jan 2018Source
  • 14 Building Plan Approval (IOD)P52100000820 · 7-8.pdf · uploaded 11 Jan 2018Source
  • 15 Building Plan Approval (IOD)P52100000820 · 8-8.pdf · uploaded 11 Jan 2018Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000820 · ARCHITECT .pdf · uploaded 26 May 2018Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000820 · PURUSHOTTAM.pdf · uploaded 26 May 2018Source
  • 2 Certificates of CA (Form 3)P52100000820 · CA CERTIFICATE ANUTHAM .pdf · uploaded 26 May 2018Source
  • 1 Certificates of CA (Form 5)P52100000820 · Audit Report.pdf · uploaded 30 Sep 2018Source
  • 16 Building Plan Approval (IOD)P52100000820 · 2 A Wing.pdf · uploaded 5 Nov 2018Source
  • 17 Building Plan Approval (IOD)P52100000820 · 3 B1 B2 Wing 1.pdf · uploaded 5 Nov 2018Source
  • 18 Building Plan Approval (IOD)P52100000820 · B1 B2 Wing 2.pdf · uploaded 5 Nov 2018Source
  • 19 Building Plan Approval (IOD)P52100000820 · Building Layout.pdf · uploaded 5 Nov 2018Source
  • 20 Building Plan Approval (IOD)P52100000820 · C Wing 1.pdf · uploaded 5 Nov 2018Source
  • 21 Building Plan Approval (IOD)P52100000820 · C Wing 2.pdf · uploaded 5 Nov 2018Source
  • 22 Building Plan Approval (IOD)P52100000820 · Parking Layout 1.pdf · uploaded 5 Nov 2018Source
  • 23 Building Plan Approval (IOD)P52100000820 · Parking Layout 2.pdf · uploaded 5 Nov 2018Source
  • 24 Building Plan Approval (IOD)P52100000820 · C LIG.pdf · uploaded 5 Nov 2018Source
  • 2 Commencement Certificates / NA Order for plotted developmentP52100000820 · CC 2018.pdf · uploaded 5 Nov 2018Source
  • 3 Proforma of Allotment letterP52100000820 · UNIT AGREEMENT DRAFT Anutham.pdf · uploaded 5 Nov 2018Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000820 · Architect Certificate-compressed.pdf · uploaded 25 Jan 2019Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)P52100000820 · Engg Certificare.pdf · uploaded 25 Jan 2019Source
  • 3 Certificates of CA (Form 3)P52100000820 · CA certificate anutham .pdf · uploaded 25 Jan 2019Source
  • 1 PAN CardP52100020764 · PAN CARD ACE.pdf · uploaded 4 May 2019Source
  • 1 Copy of the legal title reportP52100020764 · Anutham Search Report.pdf · uploaded 4 May 2019Source
  • 1 Details of encumbrancesP52100020764 · encumbrances Certificate - Hadapsar.pdf · uploaded 4 May 2019Source
  • 1 Copy of Layout Approval (in case of layout)P52100020764 · LAYOUT.pdf · uploaded 4 May 2019Source
  • 1 Building Plan Approval (IOD)P52100020764 · PLAN.pdf · uploaded 4 May 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100020764 · CC_.pdf · uploaded 4 May 2019Source
  • 1 Declaration in FORM BP52100020764 · FORM B ANUTHAM.pdf · uploaded 4 May 2019Source
  • 1 Certificates of CA (Form 3)P52100020764 · CA .pdf · uploaded 4 May 2019Source
  • 1 Proforma of Allotment letterP52100020764 · UNIT AGREEMENT DRAFT for A Wing.pdf · uploaded 4 May 2019Source
  • 2 Proforma of Allotment letterP52100020764 · UNIT AGREEMENT DRAFT for B1 Wing.pdf · uploaded 4 May 2019Source
  • 4 Proforma of Allotment letterP52100000820 · UNIT AGREEMENT DRAFT Anutham.pdf · uploaded 29 May 2019Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · hadpsar rera certificate phase -2 date -8-7-2019.pdf · uploaded 23 Jul 2019Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000820 · hadpsar rera cetificate phase 1 date - 9-7-2019-compressed.pdf · uploaded 23 Jul 2019Source
  • 2 Certificates of CA (Form 5)P52100000820 · Audit Report_Anutham.pdf · uploaded 30 Sep 2019Source
  • 3 Certificates of CA (Form 5)P52100000820 · Audit Report_Anutham.pdf · uploaded 30 Sep 2019Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · 040217082323_0001.pdf · uploaded 12 Oct 2019Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000820 · 040220094140_0001.pdf · uploaded 15 Oct 2019Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · Anutham_Phase_2.pdf · uploaded 13 Jan 2020Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000820 · Anutham_Phase_1.pdf · uploaded 13 Jan 2020Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · Anutham_RERA PHASE 2.pdf · uploaded 12 Jun 2020Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000820 · Anutham_RERA PHASE 1.pdf · uploaded 12 Jun 2020Source
  • 5 Proforma of Allotment letterP52100000820 · UNIT AGREEMENT DRAFT Anutham.pdf · uploaded 27 Aug 2020Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · Phase-2_compressed.pdf · uploaded 16 Oct 2020Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000820 · Phase-1_compressed.pdf · uploaded 16 Oct 2020Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000820 · Anutham_Phase-1.pdf · uploaded 15 Jan 2021Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000820 · MX-M265NV_20210403_153938.pdf · uploaded 3 Apr 2021Source
  • 2 Details of encumbrancesP52100020764 · encumbrances Certificate - Hadapsar.pdf · uploaded 16 Jun 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentP52100020764 · Commencement Certificate.pdf · uploaded 16 Jun 2021Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100000820 · MX-M265NV_20210717_131758.pdf · uploaded 17 Jul 2021Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)P52100000820 · SOCIETY.pdf · uploaded 4 Sep 2021Source
  • 2 Building Plan Approval (IOD)P52100020764 · 1)_11zon.pdf · uploaded 20 Sep 2021Source
  • 3 Building Plan Approval (IOD)P52100020764 · 2)_11zon.pdf · uploaded 20 Sep 2021Source
  • 4 Building Plan Approval (IOD)P52100020764 · 3)_11zon.pdf · uploaded 20 Sep 2021Source
  • 5 Building Plan Approval (IOD)P52100020764 · 4)_11zon.pdf · uploaded 20 Sep 2021Source
  • 6 Building Plan Approval (IOD)P52100020764 · 5)_11zon.pdf · uploaded 20 Sep 2021Source
  • 7 Building Plan Approval (IOD)P52100020764 · 6)_11zon.pdf · uploaded 20 Sep 2021Source
  • 8 Building Plan Approval (IOD)P52100020764 · 7)_11zon.pdf · uploaded 20 Sep 2021Source
  • 9 Building Plan Approval (IOD)P52100020764 · 8).pdf · uploaded 20 Sep 2021Source
  • 3 Commencement Certificates / NA Order for plotted developmentP52100020764 · CC.pdf · uploaded 20 Sep 2021Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · Arc_Cer-Anutham -A (Form1) Phase2.pdf · uploaded 29 Sep 2021Source
  • 3 Proforma of Allotment letterP52100020764 · UNIT AGREEMENT DRAFT - WING A - SHOP.pdf · uploaded 11 Oct 2021Source
  • 4 Proforma of Allotment letterP52100020764 · UNIT AGREEMENT DRAFT - Wing A.pdf · uploaded 11 Oct 2021Source
  • 1 Status of ConveyanceP52100000820 · CONVEYANCE DEED - B2 Wing.pdf · uploaded 11 Oct 2021Source
  • 2 Status of ConveyanceP52100000820 · CONVEYANCE DEED_C Wing.pdf · uploaded 11 Oct 2021Source
  • 3 Status of ConveyanceP52100000820 · Letter for conveyance deed registration.pdf · uploaded 11 Oct 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)P52100020764 · Form 5 Anutham Phase II Final FY 19-20_compressed (1).pdf · uploaded 1 Jan 2022Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · Anutham_A-building.pdf · uploaded 15 Jan 2022Source
  • 2 Certificates of CA (Form 3)P52100020764 · CA FORM 3.pdf · uploaded 25 Feb 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)P52100020764 · Ace Anutham Phase 2 20-21.pdf · uploaded 25 Feb 2022Source
  • 3 Certificates of CA (Form 3)P52100020764 · Anutham Phase II (1).pdf · uploaded 7 Apr 2022Source
  • 1 Declaration about Commencement CertificateP52100020764 · Form D.pdf · uploaded 13 Apr 2022Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · Anutham-A.pdf · uploaded 13 Apr 2022Source
  • 1 Disclosure of sold/ booked inventoryP52100020764 · Disclosure of Sold Booked Inventory New Format (1).pdf · uploaded 13 Apr 2022Source
  • 1 CERSAI detailsP52100020764 · CERSAI_Search_Report.pdf · uploaded 13 Apr 2022Source
  • 2 Declaration about Commencement CertificateP52100020764 · Form D.pdf · uploaded 19 Apr 2022Source
  • 4 Certificates of CA (Form 3)P52100020764 · Anutham phase II -final certificate 1.pdf · uploaded 25 Apr 2022Source
  • 5 Certificates of CA (Form 3)P52100020764 · CA Cert- Client sign copy (1).pdf · uploaded 4 Jul 2022Source
  • 6 Certificates of CA (Form 3)P52100020764 · Anutham Phase II CA certificate (2).pdf · uploaded 11 Oct 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100020764 · engg cerficate.pdf · uploaded 10 Nov 2022Source
  • 7 Certificates of CA (Form 3)P52100020764 · Anutham Phase II CA certificate sept'22.pdf · uploaded 11 Nov 2022Source
  • 1 Other – FinanceP52100000820 · Anutham C wing Form 4.pdf · uploaded 16 Feb 2023Source
  • 2 Other – FinanceP52100000820 · Anutham B2 wing Form 4.pdf · uploaded 16 Feb 2023Source
  • 8 Certificates of CA (Form 3)P52100020764 · Anutham PH II CA certificate- DEc'22 (1).pdf · uploaded 20 Feb 2023Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · arch.pdf · uploaded 21 Mar 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100020764 · Eng Certificate Dec22.pdf · uploaded 21 Mar 2023Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · ARCHITECT CERTIFICATE FORM 1 mar 23.pdf · uploaded 29 Apr 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100020764 · Engg Certificate Mar 23.pdf · uploaded 29 Apr 2023Source
  • 9 Certificates of CA (Form 3)P52100020764 · CA certificate ANutham Phase II.pdf · uploaded 29 Apr 2023Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · Architect certificate.pdf · uploaded 8 Aug 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100020764 · Engineer certificare.pdf · uploaded 8 Aug 2023Source
  • 10 Certificates of CA (Form 3)P52100020764 · CA Certificate June'23.pdf · uploaded 8 Aug 2023Source
  • 2 Disclosure of sold/ booked inventoryP52100020764 · Disclosure of Sold Booked Inventory- Anutham Phase.pdf · uploaded 6 Oct 2023Source
  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · Architect Certificate.pdf · uploaded 10 Nov 2023Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100020764 · Engineer Certificate-31 10 2023.pdf · uploaded 10 Nov 2023Source
  • 11 Certificates of CA (Form 3)P52100020764 · CA Certificate _digital Signed.pdf · uploaded 10 Nov 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)P52100020764 · 2A 2020.pdf · uploaded 16 Nov 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)P52100020764 · 2A 2021.pdf · uploaded 16 Nov 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)P52100020764 · 2A 2022.pdf · uploaded 16 Nov 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)P52100020764 · 2A 2023.pdf · uploaded 16 Nov 2023Source
  • 3 Disclosure of sold/ booked inventoryP52100020764 · Sold Booked.pdf · uploaded 16 Nov 2023Source
  • 4 Disclosure of sold/ booked inventoryP52100020764 · Disclouser.pdf · uploaded 16 Jan 2024Source
  • 3 a Details of encumbrances concerned to FinanceP52100020764 · NO DUE CERTIFICATE INDIAN BANK.pdf · uploaded 21 Feb 2024Source
  • 4 Details of encumbrancesP52100020764 · NO DUE CERTIFICATE INDIAN BANK.pdf · uploaded 21 Feb 2024Source
  • 1 b Details of encumbrances concerned to LegalP52100020764 · NO DUE CERTIFICATE INDIAN BANK.pdf · uploaded 21 Feb 2024Source
  • 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · AR Cer-Dec23.pdf · uploaded 2 Mar 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100020764 · Engg Certificate Dec23.pdf · uploaded 2 Mar 2024Source
  • 12 Certificates of CA (Form 3)P52100020764 · CA Certificate-Autham Phase II -Dec 23.pdf · uploaded 2 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100000820 · ANUTHAM PHASE I 22.pdf · uploaded 4 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P52100020764 · ANUTHAM PHASE II 21-22.pdf · uploaded 6 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100020764 · ANUTHAM PHASE II 22-23.pdf · uploaded 6 Mar 2024Source
  • 5 Disclosure of sold/ booked inventoryP52100020764 · Disclosure of Sold Booked Inventory- Anutham Phase II.pdf · uploaded 23 Apr 2024Source
  • 1 Other – TechnicalP52100020764 · Form 2A - Anutham Phase II.pdf · uploaded 23 Apr 2024Source
  • 14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · CA Cert-Autham Phase II _March 24.pdf · uploaded 21 May 2024Source
  • 15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · AR Cert-Autham Phase II _March 24.pdf · uploaded 21 May 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100020764 · ER Cert-Autham Phase II _March 24.pdf · uploaded 21 May 2024Source
  • 13 Certificates of CA (Form 3)P52100020764 · CA Cert-Autham Phase II _March 24.pdf · uploaded 21 May 2024Source
  • 6 Disclosure of sold/ booked inventoryP52100020764 · Disclosure of Sold Booked Inventory- Anutham Phase II.pdf · uploaded 18 Jul 2024Source
  • 2 Declaration in FORM BP52100020764 · Form B.pdf · uploaded 19 Jul 2024Source
  • 1 Disclosure of sold/ booked inventoryP52100020764 · Disclosure of Sold Booked Inventory- Anutham Phase II.pdf · uploaded 21 Oct 2024Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · AR JUNE .pdf · uploaded 5 Nov 2024Source
  • 1 Certificates of CA (Form 3)P52100020764 · CA Cert-Autham Phase II _June 24 Final.pdf · uploaded 5 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100020764 · Enggi Certificate.pdf · uploaded 5 Nov 2024Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)P52100020764 · Architect Certificet sept 24.pdf · uploaded 12 Apr 2025Source
  • 1 Certificates of CA (Form 3)P52100020764 · Final CA Cert-Autham Phase II Sept 24.pdf · uploaded 12 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100020764 · Engg Certificate 30092024 Anutham Phase II.pdf · uploaded 12 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryP52100020764 · Disclosure of Sold Booked Inventory- Anutham Phase II.pdf · uploaded 17 Apr 2025Source
  • Form 1P52100020764 · 1-Architect Certificate-Dec-24.pdf · uploaded 9 Jul 2025Source
  • Form 1P52100020764 · 1-Architect Certificate-March-25.pdf · uploaded 9 Jul 2025Source
  • Form 2P52100020764 · 2-Engineer Certificate-Dec-24.pdf · uploaded 9 Jul 2025Source
  • Form 2P52100020764 · 2-Engineer Certificate.pdf · uploaded 9 Jul 2025Source
  • Form 3P52100020764 · 3-CA Certificate-Dec-24 final.pdf · uploaded 9 Jul 2025Source
  • Form 3P52100020764 · 3-Final CA Certificate-March-25.pdf · uploaded 9 Jul 2025Source
  • Disclosure of Sold and Booked InventoryP52100020764 · Disclosure of Sold Booked Inventory- Anutham Phase II.pdf · uploaded 9 Jul 2025Source
  • Disclosure of Sold and Booked InventoryP52100020764 · Disclosure of Sold Booked Inventory- Anutham Phase.pdf · uploaded 9 Jul 2025Source
  • Form 1P52100020764 · AR june 25.pdf · uploaded 12 Sep 2025Source
  • Form 2P52100020764 · ER june 25.pdf · uploaded 12 Sep 2025Source
  • Form 3P52100020764 · CA june 25 final.pdf · uploaded 12 Sep 2025Source
  • Disclosure of Sold and Booked InventoryP52100020764 · Disclosure of sold - anutham phase 2.pdf · uploaded 12 Sep 2025Source
  • Form 1P52100020764 · AR JUNE 24.pdf · uploaded 26 Sep 2025Source
  • Form 1P52100020764 · Architect Certificet sept 24.pdf · uploaded 26 Sep 2025Source
  • Form 2P52100020764 · Enggi Certificate jun 24.pdf · uploaded 26 Sep 2025Source
  • Form 2P52100020764 · Engg Certificate 30092024 Anutham Phase II.pdf · uploaded 26 Sep 2025Source
  • Form 3P52100020764 · CA Cert-Autham Phase II _June 24 Final.pdf · uploaded 26 Sep 2025Source
  • Form 3P52100020764 · Final CA Cert-Autham Phase II Sept 24.pdf · uploaded 26 Sep 2025Source
  • Disclosure of Sold and Booked InventoryP52100020764 · Disclosure of Sold Booked Inventory jun 24.pdf · uploaded 26 Sep 2025Source
  • Disclosure of Sold and Booked InventoryP52100020764 · Disclosure of Sold Booked Inventory- Anutham Phase II.pdf · uploaded 26 Sep 2025Source
  • Form 5 (FY 2023-2024)P52100020764 · Form 5 -Autham Phase II 2023-24.pdf · uploaded 26 Sep 2025Source
  • Withdrawal Update Form 1P52100020764 · AR june 25.pdf · uploaded 12 Dec 2025Source
  • Withdrawal Update Form 2P52100020764 · ER june 25.pdf · uploaded 12 Dec 2025Source
  • Withdrawal Update Form 3P52100020764 · CA june 25 final.pdf · uploaded 12 Dec 2025Source
  • Form 5 (FY 2024-2025)P52100020764 · Rera Audit Report -2024-25.pdf · uploaded 3 Jan 2026Source
  • Form 2A (FY 2019-2020)P52100020764 · Form 2A- march 20.pdf · uploaded 4 Jun 2026Source
  • Form 2A (FY 2020-2021)P52100020764 · Form 2A- march 21.pdf · uploaded 4 Jun 2026Source
  • Form 2A (FY 2021-2022)P52100020764 · Form 2A- march 22.pdf · uploaded 4 Jun 2026Source
  • Form 2A (FY 2022-2023)P52100020764 · Form 2A- march 22.pdf · uploaded 4 Jun 2026Source
  • Form 2A (FY 2023-2024)P52100020764 · Form 2A- march 24.pdf · uploaded 4 Jun 2026Source
  • Form 2A (FY 2024-2025)P52100020764 · Form 2A- march 25.pdf · uploaded 4 Jun 2026Source
  • Form 2A (FY 2025-2026)P52100020764 · Form 2A- march 26.pdf · uploaded 4 Jun 2026Source
  • Form 2A (FY 2024-2025)P52100020764 · Form 2A- march 25.pdf · uploaded 4 Jun 2026Source
  • Form 2A (FY 2025-2026)P52100020764 · Form 2A- march 26.pdf · uploaded 4 Jun 2026Source
  • Withdrawal Update Form 1P52100020764 · AR june 25.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 1P52100020764 · AR june 25.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 1P52100020764 · AR june 25.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 1P52100020764 · AR june 25.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 2P52100020764 · ER june 25.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 2P52100020764 · ER june 25.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 2P52100020764 · ER june 25.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 2P52100020764 · ER june 25.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 3P52100020764 · CA june 25 final.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 3P52100020764 · CA june 25 final.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 3P52100020764 · CA june 25 final.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 3P52100020764 · CA june 25 final.pdf · uploaded 18 Sep 2026Source
  • Form 5 (FY 2025-2026)P52100020764 · Ace Construction - Form 5- Anutham Ph II.pdf · uploaded 30 Sep 2026Source

Technical

  • DocumentP52100000820 · ANUTHAM Amalgamation.pdf · uploaded 19 Jul 2017Source
  • DocumentP52100000820 · ANUTHAM B1 B2.pdf · uploaded 19 Jul 2017Source
  • DocumentP52100000820 · ANUTHAM C.pdf · uploaded 19 Jul 2017Source
  • DocumentP52100000820 · ANUTHAM C-.pdf · uploaded 19 Jul 2017Source
  • DocumentP52100000820 · ANUTHAM Elevation ABC.pdf · uploaded 19 Jul 2017Source
  • DocumentP52100000820 · ANUTHAM LIG.pdf · uploaded 19 Jul 2017Source
  • DocumentP52100000820 · ANUTHAM Parking Layout.pdf · uploaded 19 Jul 2017Source
  • DocumentP52100000820 · Layout.pdf · uploaded 19 Jul 2017Source
  • DocumentP52100000820 · 1-8.pdf · uploaded 11 Jan 2018Source
  • DocumentP52100000820 · 3-8.pdf · uploaded 11 Jan 2018Source
  • DocumentP52100000820 · 4-8.pdf · uploaded 11 Jan 2018Source
  • DocumentP52100000820 · 5-8.pdf · uploaded 11 Jan 2018Source
  • DocumentP52100000820 · 6-8.pdf · uploaded 11 Jan 2018Source
  • DocumentP52100000820 · 7-8.pdf · uploaded 11 Jan 2018Source
  • DocumentP52100000820 · 8-8.pdf · uploaded 11 Jan 2018Source
  • DocumentP52100000820 · 2-8.pdf · uploaded 11 Jan 2018Source
  • DocumentP52100000820 · 2 A Wing.pdf · uploaded 5 Nov 2018Source
  • DocumentP52100000820 · 3 B1 B2 Wing 1.pdf · uploaded 5 Nov 2018Source
  • DocumentP52100000820 · B1 B2 Wing 2.pdf · uploaded 5 Nov 2018Source
  • DocumentP52100000820 · Building Layout.pdf · uploaded 5 Nov 2018Source
  • DocumentP52100000820 · C Wing 1.pdf · uploaded 5 Nov 2018Source
  • DocumentP52100000820 · C Wing 2.pdf · uploaded 5 Nov 2018Source
  • DocumentP52100000820 · Parking Layout 1.pdf · uploaded 5 Nov 2018Source
  • DocumentP52100000820 · Parking Layout 2.pdf · uploaded 5 Nov 2018Source
  • DocumentP52100000820 · C LIG.pdf · uploaded 5 Nov 2018Source
  • DocumentP52100020764 · LAYOUT.pdf · uploaded 4 May 2019Source
  • DocumentP52100020764 · PLAN.pdf · uploaded 4 May 2019Source
  • DocumentP52100020764 · 1)_11zon.pdf · uploaded 20 Sep 2021Source
  • DocumentP52100020764 · 2)_11zon.pdf · uploaded 20 Sep 2021Source
  • DocumentP52100020764 · 3)_11zon.pdf · uploaded 20 Sep 2021Source
  • DocumentP52100020764 · 4)_11zon.pdf · uploaded 20 Sep 2021Source
  • DocumentP52100020764 · 5)_11zon.pdf · uploaded 20 Sep 2021Source
  • DocumentP52100020764 · 6)_11zon.pdf · uploaded 20 Sep 2021Source
  • DocumentP52100020764 · 7)_11zon.pdf · uploaded 20 Sep 2021Source
  • DocumentP52100020764 · 8).pdf · uploaded 20 Sep 2021Source
  • Other – TechnicalP52100020764 · Form 2A - Anutham Phase II.pdf · uploaded 23 Apr 2024Source

Technical (Architect)

  • DocumentP52100000820 · MX-M265NV_20210717_131758.pdf · uploaded 17 Jul 2021Source
  • DocumentP52100020764 · AR JUNE .pdf · uploaded 5 Nov 2024Source
  • DocumentP52100020764 · Architect Certificet sept 24.pdf · uploaded 12 Apr 2025Source
  • DocumentP52100020764 · AR june 25.pdf · uploaded 18 Sep 2026Source

Technical (Engineer)

  • DocumentP52100000820 · Engg Certificare.pdf · uploaded 25 Jan 2019Source
  • DocumentP52100020764 · Enggi Certificate.pdf · uploaded 5 Nov 2024Source
  • DocumentP52100020764 · Engg Certificate 30092024 Anutham Phase II.pdf · uploaded 12 Apr 2025Source
  • DocumentP52100020764 · ER june 25.pdf · uploaded 18 Sep 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Hadapsar, Haveli taluka

Survey, CTS, gat or plot numbers

257AS NO. 257

Boundaries

North
Pune Solapur Road
South
Canal
East
Lohiya Garden
West
Amar Deep Society

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectElement Five—P52100000820
ArchitectELEMENT FIVE Jaideep Deshpande—P52100020764
Chartered accountantCA Paresh P. Sabadra—P52100020764
EngineerAkhil Shaikh—P52100020764
EngineerPurushottam Dimble—P52100020764
EngineerSahil Devkar—P52100020764
EngineerSpectrum Consultant—P52100000820
OtherManish Group Pvt Ltd—P52100020764
OtherVastu Yash Constructions—P52100000820

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology