Skip to content

C · Anutham

Hadapsar · RERA P52100000820

IDBLD_02708223 floorsPromised date passed
23Sanctioned habitable floorsregistration certificate
30 Dec 2021Revised completionpromised 30 Dec 2021
62 of 62Units bookedMahaRERA project page

Floors

23 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100000820 · registered 23 Jul 2017
Promised completion
30 Dec 2021
Revised completion
30 Dec 2021
Sanctioned habitable floors
23
ProjectId
4,954
ProjectName
ANUTHAM PHASE 1
TotalUnitCount
0
ProjectBuildingId
42,849
BuildingNameNumber
C
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P52100000820
ProjectBuildingWingsId
42,849
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
C
NoOfBuildingWingFloorProposed
23
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
23

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1 BHK31.5 m² (339 sq.ft)1010
2 BHK32.1 m² (345 sq.ft)88
2 BHK32.2 m² (346 sq.ft)1414
2 BHK32.2 m² (346 sq.ft)22
2 BHK36.3 m² (391 sq.ft)88
2 BHK46.3 m² (498 sq.ft)44
2 BHK46.4 m² (499 sq.ft)44
2BHK40.3 m² (434 sq.ft)11
2BHK40.6 m² (437 sq.ft)88
2BHK40.6 m² (437 sq.ft)11
2BHK43 m² (463 sq.ft)22
Total6262
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology