Abubakar Ali Mohammed Zariwala
Deedo IDDD-GK0COf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| BellamonteP51700014313 | Thane (M Corp.) | Certificate Signed | 28 May 2021 | 28 Nov 2022 | +18 mo |
Abubakar Ali Mohammed Zariwala, in questions
Does Abubakar Ali Mohammed Zariwala finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.
How many projects has Abubakar Ali Mohammed Zariwala registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Abubakar Ali Mohammed Zariwala have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.