Deedo IDDD-25QG

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 23 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay23 mowhen late
First sales on record2registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
AcropolisP52100013246Uruli KanchanCertificate Signed30 Dec 202430 Dec 2024+23 mo*

Abhijeet Subhash Kanchan, in questions

Does Abhijeet Subhash Kanchan finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.

How many projects has Abhijeet Subhash Kanchan registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Abhijeet Subhash Kanchan have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology