Of 1 registration whose promised date has arrived, 1 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Atharva Bliss Phase IP52100006701Bavadhan BkCertificate Signed31 Dec 201731 Dec 2017On date
Atharva Bliss Phase II- Amenity BuildingP52100080179Bavadhan BkCertificate Signed31 Mar 202931 Jul 2029+4 mo
Atharva Bliss Phase II- Residential BuildingP52100080855Bavadhan BkCertificate Signed31 Mar 202931 Jul 2029+4 mo

Abhay Constructions, in questions

Does Abhay Constructions finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Abhay Constructions registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.

Does Abhay Constructions have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology