Abhavya Reality
Deedo IDDD-YEGSOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Rama Krishna ApartmentP52000021341 | Wahal | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| Abhavya PrideP52000021403 | Wahal | Certificate Signed | 30 May 2023 | 29 May 2024 | +12 mo |
Abhavya Reality, in questions
Does Abhavya Reality finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Abhavya Reality registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Abhavya Reality have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.